AC Unit Electrical Requirements: 2026 Contractor Guide

PES Supply, a PES Global Group Company
· 14 min read Reviewed by PES Supply editorial team
AC Unit Electrical Requirements — Contractor Guide 2026

Table of Contents

    AC Unit Electrical Requirements: 2026 Contractor Guide

    Breaker sizing, wire gauge, disconnect placement, and NEC 440 compliance for central air conditioners, heat pumps, and mini-split installations.

    Every air conditioner — whether a 3-ton central unit or a 12k BTU mini split — is a continuous load that defines the circuit it sits on. Get the breaker, wire, or disconnect wrong and you get callbacks, failed inspections, or compressor damage. I've seen a $12,000 compressor replacement because the electrician pulled 12 AWG for a 4-ton unit that needed 8 AWG. The wire overheated, the voltage dropped, and the compressor ran starved for 18 months before it seized.

    This guide is the electrical side of AC installation: breaker sizing, wire gauge, disconnect placement, and the NEC rules that actually matter in 2026. Portlandia Electric Supply does not stock HVAC equipment — we stock the electrical infrastructure that makes it run: breakers, wire, conduit, disconnects, panels, and transfer switches. If you are sizing the circuit, you are in the right place. For condenser-specific details, see our AC Condenser Electrical Requirements guide. For furnace circuits, see the Furnace Contractor Guide.

    AC Unit Electrical Requirements at a Glance

    This table covers central AC, heat pumps, and mini-splits. Breaker sizes are HACR-rated. Wire is copper THHN/THWN-2 at 75°C.

    AC Type Typical Load Breaker Wire (Cu) Disconnect NEC Article
    1.5-ton central (18k BTU) 12–15A running 25–30A 10 AWG Fused or non-fused 30A 440
    2-ton central (24k BTU) 14–18A running 30A 10 AWG Fused or non-fused 30A 440
    2.5-ton central (30k BTU) 18–22A running 35–40A 8 AWG Fused or non-fused 40–60A 440
    3-ton central (36k BTU) 20–25A running 40–45A 8 AWG Fused or non-fused 60A 440
    3.5-ton central (42k BTU) 25–30A running 45–50A 8 AWG / 6 AWG Fused or non-fused 60A 440
    4-ton central (48k BTU) 28–32A running 50A 6 AWG Fused or non-fused 60A 440
    5-ton central (60k BTU) 35–40A running 60A 6 AWG Fused or non-fused 60A 440
    Heat pump 3-ton 22–28A running 40–50A 8 AWG Fused or non-fused 60A 440
    Heat pump 5-ton 35–42A running 60A 6 AWG Fused or non-fused 60A 440
    Mini split 9k–12k BTU 5–10A running 15–20A 12 AWG Shutoff within sight (15–20A) 440
    Mini split 18k–24k BTU 10–16A running 20–25A 12 AWG / 10 AWG Shutoff within sight (20–30A) 440
    Mini split 36k BTU 16–22A running 30A 10 AWG Shutoff within sight (30A) 440

    Key rule: Compressors are motor loads. NEC 440 applies, not the standard branch-circuit sizing in Article 310. Breakers are sized to handle locked-rotor amperage (LRA) on startup — often 5–7× running amps — which is why a 15A-running compressor needs a 30A breaker. I've had apprentices argue that 14 AWG on a 15A breaker should work for a mini split. It won't. The LRA on a 12k BTU mini split can hit 45A for half a second. The HACR breaker handles that. A standard breaker trips.

    Breaker Sizing: NEC 440.22 Deep Dive

    Article 440 gives two methods for sizing overcurrent protection:

    1. Standard method (440.22(A)): Breaker size = 175% of rated-load current (RLA) or branch-circuit selection current (whichever is larger). Round up to the next standard breaker size.
    2. Alternate method (440.22(B)): Breaker = 225% of RLA. Only permitted if the breaker does not trip under normal starting — and you must use time-delay fuses or HACR-rated breakers.
    Unit Size RLA LRA Std Method (×1.75) Breaker Alt Method (×2.25) Breaker
    2-ton 11A 58A 19.3A 20A HACR 24.8A 25A HACR
    2.5-ton 14A 72A 24.5A 25A HACR 31.5A 35A HACR
    3-ton 17A 95A 29.8A 30A HACR 38.3A 40A HACR
    3.5-ton 20A 110A 35.0A 35A HACR 45.0A 45A HACR
    4-ton 23A 125A 40.3A 40A HACR 51.8A 50A HACR*
    5-ton 28A 145A 49.0A 50A HACR 63.0A 60A HACR*

    *Alternate method limited by nameplate MOP. If MOP is 50A, you cannot use the alternate method result of 51.8A. The nameplate governs.

    Practical example: a 3-ton condenser rated 17A RLA / 95A LRA. Standard method: 17A × 1.75 = 29.75A → 30A breaker (HACR-rated). Alternate: 17A × 2.25 = 38.25A → 40A breaker with HACR rating. Most condenser nameplates list "Max Fuse / HACR Breaker" — size to that. Never exceed the nameplate maximum. I had a job in Texas where the nameplate said 35A MOP but the electrician installed a 40A because "that's what we always use on 3-ton units." The inspector caught it. The breaker came out. The drywall patch cost $300.

    Wire Gauge: Account for Conduit Fill and Ambient

    Do not size wire to the breaker — size to the load with proper derating:

    • Attic runs: Ambient can hit 55–65°C. NEC 310.15(B)(2) derates THHN from 75°C ampacity. A 10 AWG THHN rated 35A at 75°C drops to ~28A in a hot attic with three current-carrying conductors. For a 22A compressor in attic conduit, 8 AWG is the safe call. I learned this the hard way on a Houston job in July. The attic was 140°F. The 10 AWG was smoking.
    • NM-B (Romex): Limited to 60°C ampacity. 10 AWG NM-B = 30A. For a 25A load, you are at 83% — legal, but hot. Upsize to 8 AWG NM-B or run THHN in conduit. I do not spec NM-B for AC circuits over 20A. The temperature derating kills you.
    • Conduit runs to pad-mount: Use THHN/THWN-2 in PVC or EMT. Wet locations require W-rated insulation. EMT is my preference — it provides physical protection and an equipment grounding path if properly bonded.
    Wire Type 10 AWG Rating 8 AWG Rating 6 AWG Rating Best Use Case
    THHN/THWN-2 (75°C) 35A 50A 65A Conduit runs, outdoor
    THHN (60°C) 30A 40A 55A Rarely used now
    NM-B (60°C) 30A 40A 55A Indoor branch circuits
    THHN/THWN-2 (3 conductors, 45°C attic) 28A 40A 52A Attic runs (derated)
    THHN/THWN-2 (6 conductors, 45°C attic) 24A 35A 45A Conduit fill + derating

    The Disconnect: NEC 440.14 and 430.102

    AC condensers require a disconnect within sight and within 50 feet of the unit:

    • Fused disconnect: Provides overcurrent protection if the breaker is remote. Common on commercial and multi-unit installs. I use fused disconnects when the breaker panel is in a mechanical room 80 feet from the condenser.
    • Non-fused (pullout) disconnect: Cheaper, lighter, but relies on the upstream breaker. Standard on residential split systems. We sell thousands of these — the 30A non-fused disconnect at $99.99 is our top seller.
    • Lockable: Required in many jurisdictions for service access and OSHA lockout/tagout compliance. If the disconnect does not have a hasp, add one. Inspectors check this.

    Mini splits are simpler: most inverter-driven units have an integral disconnect or require only a shutoff within sight. Check the installation manual — some brands require a dedicated disconnect; others accept the breaker as the disconnecting means if it's within sight. Mitsubishi, Daikin, and LG all have different requirements. I keep a binder of installation manuals in the truck. Saves callbacks.

    Panel Capacity: Will the Board Take It?

    A 3-ton central AC on a 30A 240V circuit draws ~7.2kW. On a 200A service, that is fine. On a 100A service already feeding electric range, dryer, and water heater, a NEC 220.83 load calculation often fails. Common fixes:

    1. Load-shed device: Automatically drops the water heater or EV charger when the AC starts. Cheaper than a panel upgrade. The Generac Load Control Module handles up to 50A of managed load.
    2. Subpanel: Feed a new 60A subpanel from spare lugs or a dual-feed breaker if the main has capacity. We stock Square D and Siemens subpanels for exactly this scenario.
    3. Service upgrade to 200A: The right answer if you are also adding a heat pump, EV circuit, or home battery later. A 200A service upgrade runs $2,500–$4,500 in most markets. Factor it into the proposal if the load calc is close.

    NEC 220.83 Load Calculation Trap

    Many contractors skip the formal load calc for a simple AC addition. Do not. If the existing service is 100A and the home has electric cooking, the addition of a 30A AC circuit may push the calculated load over 100A. The inspector will ask for the load calc. Have it ready. We provide load calculation worksheets through our Pro Account portal.

    Mini Split Wiring: The High-Voltage and Low-Voltage Split

    Mini splits run two cables that must be kept separate:

    • Line set (refrigerant): Not electrical — but the condensate pump and line-set penetration need compliance with local mechanical codes.
    • Power (high voltage): 240V to the outdoor unit, typically 10–12 AWG depending on amperage and run length. Some small single-zone units run 120V. Always check the nameplate — I've seen 9k BTU units that need 20A 240V circuits because of inverter inrush.
    • Control (low voltage): 14–18 AWG two-conductor between indoor head and outdoor condenser. Manufacturer-specified; do not substitute thermostat wire unless the spec allows it. Mitsubishi uses shielded 18/2. LG uses unshielded 16/2. Using the wrong cable can cause communication errors and fault codes.

    Max run length: Most manufacturers spec 25–50 feet of line set without refrigerant charge adjustment. Beyond that, wire voltage drop matters too — keep 240V drops under 3%. For a 20A mini split circuit, 10 AWG is good to 80 feet. At 100 feet, upsize to 8 AWG.

    Mini Split Size Running Amps Breaker Power Wire Control Wire Max Line Set
    9k BTU (0.75 ton) 4–6A 15A 14 AWG 18/2 shielded 25 ft
    12k BTU (1 ton) 5–8A 15–20A 14 AWG 18/2 shielded 25 ft
    18k BTU (1.5 ton) 8–12A 20A 12 AWG 16/2 unshielded 35 ft
    24k BTU (2 ton) 10–15A 20–25A 12 AWG 16/2 unshielded 50 ft
    36k BTU (3 ton) 16–20A 25–30A 10 AWG 16/2 unshielded 65 ft
    Multi-zone (2–4 heads) 15–25A 25–35A 10 AWG 16/2 per head 65 ft

    How to Wire an AC Unit Circuit

    Step 1: Perform Load Calculation

    Before you add a 30A circuit to a 100A panel, run the numbers. NEC 220.83 gives you an optional calculation for existing dwellings. Add the existing loads (general lighting, appliances, HVAC) and compare to the service rating. If the calculated load exceeds 80% of service rating, you need a service upgrade or load management. I keep a spreadsheet template on my phone. Takes 5 minutes and saves hours of rework.

    Step 2: Select HACR Breaker

    Read the nameplate RLA. Multiply by 1.75. Round to the next standard breaker size. Verify the result is ≤ MOP. If it is not, use the nameplate MOP as your breaker size and verify the wire still handles the MCA. Order the breaker before you start — HACR breakers in 25A, 35A, and 45A can be special-order items at big-box stores. We stock them for next-day delivery.

    Step 3: Size Conductors

    Use NEC Table 310.16 at 75°C. For a 30A circuit, 10 AWG THHN is rated 35A — adequate for MCA up to 28A. But if the run passes through a 130°F attic with two other circuits in the same conduit, derating applies. Three current-carrying conductors at 55°C ambient: derating factor 0.71. 35A × 0.71 = 24.9A. If MCA is 22A, you are legal but tight. I upsize to 8 AWG and forget about it.

    Step 4: Install Disconnect

    Within sight means visible and not more than 50 feet away. Mount the disconnect between 4 and 6 feet above grade. Face it so the HVAC technician can read the label from the service position. Use raintight fittings on the bottom. Weep holes down. I've seen disconnects mounted upside down with water pooling inside. Rusted contacts. Failed inspection.

    Step 5: Run Conduit and Wire

    EMT is my preference for commercial. PVC Schedule 80 for residential pad-mount condensers. Minimum burial depth: 18 inches for PVC (NEC Table 300.5). Use expansion fittings where the conduit exits the slab — freeze-thaw will crack rigid PVC without them. For the whip from disconnect to condenser, use liquid-tight flexible metal conduit (LFMC) with raintight connectors. Length should not exceed 6 feet per NEC 440.14.

    Step 6: Ground and Bond

    Run a dedicated equipment grounding conductor. Do not rely on the conduit alone, even though EMT is an acceptable grounding path per 250.118. A separate green wire gives you redundancy and makes troubleshooting easier. Bond the condenser frame with a grounding lug and anti-oxidant compound on aluminum enclosures.

    Step 7: Label and Inspect

    Label the disconnect "AC Condenser" with the circuit number. Update the panel directory. If this is a subpanel, add a placard showing the feeder source. Megger the circuit at 500V DC — you want 100 MΩ or higher. Below 25 MΩ and I start hunting for a nail through the cable. Schedule inspection before the HVAC crew charges the system. Once refrigerant is in, the electrical inspector may not want the unit powered for testing.

    Permits and Inspections

    In virtually every U.S. jurisdiction, a new AC circuit requires:

    • Electrical permit for the new 240V branch circuit.
    • HVAC permit for the refrigerant work (if you are the mechanical contractor).
    • Inspection of the disconnect location, wire gauge, breaker sizing, and grounding.

    Common inspection failures: disconnect not within sight, undersized ground (must match circuit ground, not the smaller control wire), NM-B run underground without conduit, and breaker not HACR-rated. I've also seen failures for missing weep holes in PVC conduit, unsupported EMT sagging more than 1/4 inch per foot, and unlabeled subpanels. The inspectors are not being difficult — they are checking the same items that cause fires and electrocutions.

    FAQ: AC Unit Electrical

    What size breaker for a 3-ton AC unit?

    30–35A HACR-rated. Calculate from RLA × 1.75. If RLA is 17A, 17 × 1.75 = 29.75A → 30A breaker. If the nameplate MOP is 30A, you are at the limit. If MOP is 35A, you have options. Never guess — read the plate.

    What wire for a 30-amp AC circuit?

    10 AWG THHN in conduit for standard conditions. 8 AWG if the run is over 75 feet, in a hot attic, or with multiple circuits in one conduit. NM-B is limited to 30A at 60°C and cannot be used outdoors.

    Does a mini split need a disconnect?

    Yes. NEC 440.14 applies to all air conditioning equipment. Some mini split manufacturers accept the breaker as the disconnect if it is within sight. Others — especially multi-zone systems — require a dedicated shutoff at the outdoor unit. The installation manual governs.

    Can I use a standard breaker for AC?

    No. Standard thermal-magnetic breakers trip on compressor LRA. HACR breakers have magnetic trip curves that tolerate the 5–7× inrush for a few cycles. The difference is engineered. The markup is $3–$8 per breaker. Use the right one.

    How far can the disconnect be from the AC unit?

    50 feet and within sight. That means the technician standing at the unit can see the disconnect handle and reach it without tools. If a fence blocks the view, move the disconnect or cut a sight window.

    What is the 125% rule for AC?

    NEC 440.6 requires branch-circuit conductors to carry 125% of RLA. A 20A RLA compressor needs 25A conductor ampacity. Since 12 AWG is only 20A at 60°C, you need 10 AWG (35A at 75°C). The 125% rule is why even "small" ACs often need 10 AWG.

    Can I run NM-B to an outdoor condenser?

    No. NM-B is for dry, interior locations. Outdoor condensers are wet locations with physical damage potential. Use THHN/THWN-2 in EMT or PVC. The W rating is for wet — it matters.

    What is the difference between MCA and RLA?

    RLA is what the compressor draws at full load. MCA is what the wire must handle — RLA × 1.25 plus condenser fan amps. Always size wire to MCA. Size breaker to MOP. Those are the two numbers that matter.

    Electrical Components in Stock

    Portlandia Electric Supply stocks the electrical infrastructure AC contractors need: breakers and panels, wire and conduit, AC disconnects, and load management devices. For project-specific quantities and contractor pricing, request a quote — we ship nationwide with same-day fulfillment on orders before 2 PM ET.

    Related Resources

    Contractor-Grade Electrical Supply

    Breakers, wire, conduit, disconnects, and panels shipped direct to your job site. Bulk pricing available through PowerLink Network.

    Get a Quote

    Need Help Sizing This?

    Our team can help you calculate loads, select the right equipment, and source everything from one PO.

    📞 (502) 790-0600

    Email Our Team
    Solar Panels Generators Batteries / ESS EV Chargers Circuit Breakers Charge Controllers

    One PO. One Invoice. Every Trade Covered.

    PES Supply is the distribution arm of PES Global Group — 50,000+ SKUs from 169 authorized brands, LTL freight shipping from Louisville, KY.

    Get a Quote
    Share: X f in @

    Related Articles

    Solar panel installation cost guide 2026

    How Much Does It Cost to Install Solar Panels in 2026? A ...

    Aug 28, 2026
    300 Watt Solar Panels in 2026: Legacy Stock Guide, Pricing & Modern Alternatives

    300 Watt Solar Panels in 2026: Legacy Stock Guide, Pricin...

    Aug 26, 2026
    500-watt solar panels with black monocrystalline cells and silver aluminum frames

    500 Watt Solar Panel Buyer's Guide: Best Models, Specs & ...

    Aug 24, 2026
    Pure Sine Wave Inverter: 2026 Buyer's Guide for Installers & Off-Grid Builders

    Pure Sine Wave Inverter: 2026 Buyer's Guide for Installer...

    Aug 21, 2026
    Close-up of two different solar microinverter/optimizer units mounted under rooftop panels

    Enphase vs Tigo 2026: Microinverters vs Selective MLPE De...

    Aug 10, 2026
    Electrical contractor inspecting AC condenser disconnect and wiring

    AC Condenser Electrical Requirements — 2026 Contractor Guide

    Aug 10, 2026
    Two premium residential solar panel arrays on neighboring rooftops in a sunny suburb

    REC Alpha Pure-RX vs Qcells Q.TRON: Premium Residential P...

    Aug 06, 2026
    Furnace — 2026 Contractor Guide

    Furnace — 2026 Contractor Guide

    Aug 04, 2026
    Level 2 EV wall charger in a clean residential garage with an electric vehicle plugged in, warm lighting

    Level 2 EV Charger Buyer's Guide 2026: Amperage, NEMA 14-...

    Aug 03, 2026
    Collage of 2026 solar trends: TOPCon panels, battery storage, and AI-monitored rooftop arrays

    Top 10 Solar Industry Trends Shaping Q3 2026

    Jul 31, 2026
    NEC 2026 code book beside a solar inverter and rapid-shutdown wiring on a rooftop

    NEC 2026 Code Changes: Top 10 Updates Affecting Solar Ins...

    Jul 28, 2026
    EG4 Solar Equipment Guide: 18kPV & XP Inverters, Batteries & Chargeverter Explained

    EG4 Solar Equipment Guide: 18kPV & XP Inverters, Batterie...

    Jul 23, 2026
    A lineup of four residential standby generators of increasing physical size on a concrete pad next to a suburban home

    12kW vs 16kW vs 20kW vs 24kW Standby Generator: Which Siz...

    Jul 12, 2026
    Three standby generator setups showing a natural gas meter connection

    Natural Gas vs Propane vs Diesel Standby Generators

    Jul 12, 2026
    A modern residential rooftop with bifacial solar panels and a single-axis tracking test rig

    Build a 2026 residential solar simulator: calculate outpu...

    Jul 11, 2026
    Three solar panel types on comparison racks on a residential roof

    Compare 2026 solar tech: TOPCon vs HJT vs Tandem - effici...

    Jul 09, 2026
    Victron vs OutBack 2026: MPPT Charge Controllers Compared

    Victron vs OutBack 2026: MPPT Charge Controllers Compared

    Jul 08, 2026
    Victron vs Morningstar 2026: MPPT Charge Controllers Compared

    Victron vs Morningstar 2026: MPPT Charge Controllers Comp...

    Jul 07, 2026
    Victron MultiPlus vs Sol-Ark 2026: Component vs All-in-One Hybrid Design

    Victron MultiPlus vs Sol-Ark 2026: Component vs All-in-On...

    Jul 06, 2026
    Concrete ballast blocks securing a flat-roof commercial solar array

    Solar Ballast Blocks Guide: Types, Sizing, Installation, ...

    Jul 06, 2026
    Trina vs JinkoSolar 2026: Vertex S+ vs Tiger Neo

    Trina vs JinkoSolar 2026: Vertex S+ vs Tiger Neo

    Jul 01, 2026
    TOPCon vs HJT Solar Panels 2026: N-Type Cell Technology Compared

    TOPCon vs HJT Solar Panels 2026: N-Type Cell Technology C...

    Jun 30, 2026
    SolarEdge vs Tigo 2026: Full Optimizer Systems vs Selective MLPE

    SolarEdge vs Tigo 2026: Full Optimizer Systems vs Selecti...

    Jun 29, 2026
    SolarEdge vs Hoymiles 2026: Optimizers vs 4-in-1 Microinverters

    SolarEdge vs Hoymiles 2026: Optimizers vs 4-in-1 Microinv...

    Jun 24, 2026
    Sol-Ark vs Sungrow 2026: Hybrid Inverter Philosophies Compared

    Sol-Ark vs Sungrow 2026: Hybrid Inverter Philosophies Com...

    Jun 23, 2026
    Sol-Ark vs Generac PWRcell 2026: Open Hybrid vs Ecosystem Storage

    Sol-Ark vs Generac PWRcell 2026: Open Hybrid vs Ecosystem...

    Jun 22, 2026
    A clean wall display of modern residential solar inverters in a bright showroom

    Top 10 Solar Inverters That Deliver Maximum Savings in 2026

    Jun 19, 2026
    Two hybrid solar inverters mounted side by side on a utility wall

    Sol-Ark vs EG4 Hybrid Inverters: 12K/15K vs 12KPV/18KPV

    Jun 17, 2026
    SMA vs Fronius 2026: European String Inverter Giants Compared

    SMA vs Fronius 2026: European String Inverter Giants Comp...

    Jun 16, 2026
    REC vs VSUN 2026: Premium HJT vs Value Tier-1 Panels

    REC vs VSUN 2026: Premium HJT vs Value Tier-1 Panels

    Jun 15, 2026
    REC vs Silfab 2026: Premium Import vs North American-Made Panels

    REC vs Silfab 2026: Premium Import vs North American-Made...

    Jun 10, 2026
    REC vs Canadian Solar 2026: Premium HJT vs Best-Value Tier-1

    REC vs Canadian Solar 2026: Premium HJT vs Best-Value Tier-1

    Jun 08, 2026
    A homeowner and a solar consultant reviewing paperwork at a kitchen table with a rooftop solar array visible through the window

    Lease vs. Loan vs. Cash: Which Solar Option is Best?

    Jun 07, 2026
    QCells vs VSUN 2026: US-Made TOPCon vs Value Import TOPCon

    QCells vs VSUN 2026: US-Made TOPCon vs Value Import TOPCon

    Jun 03, 2026
    QCells vs Silfab 2026: The Two North American-Made Panel Champions

    QCells vs Silfab 2026: The Two North American-Made Panel ...

    Jun 02, 2026
    QCells vs Canadian Solar 2026: Georgia vs Texas — US-Made TOPCon Battle

    QCells vs Canadian Solar 2026: Georgia vs Texas — US-Made...

    Jun 01, 2026
    Pylontech vs BYD 2026: Rack vs Tower LFP Batteries

    Pylontech vs BYD 2026: Rack vs Tower LFP Batteries

    May 27, 2026
    OutBack vs Schneider 2026: The Two Premium Off-Grid Inverter Legacies

    OutBack vs Schneider 2026: The Two Premium Off-Grid Inver...

    May 26, 2026
    Mission Solar vs Aptos 2026: US-Made Panels Compared

    Mission Solar vs Aptos 2026: US-Made Panels Compared

    May 20, 2026
    Two MPPT solar charge controllers mounted side by side in a power room

    MidNite vs Victron Charge Controllers: Classic vs SmartSolar

    May 19, 2026
    MidNite vs Morningstar 2026: American MPPT Controllers

    MidNite vs Morningstar 2026: American MPPT Controllers

    May 18, 2026
    LiFePO4 vs AGM Batteries 2026: The Honest Cost Comparison

    LiFePO4 vs AGM Batteries 2026: The Honest Cost Comparison

    May 13, 2026
    Kohler vs Cummins 2026: Premium Standby Generators Compared

    Kohler vs Cummins 2026: Premium Standby Generators Compared

    May 12, 2026
    Kohler vs Briggs & Stratton 2026: Standby Generator Shootout

    Kohler vs Briggs & Stratton 2026: Standby Generator Shootout

    May 11, 2026
    JA Solar vs JinkoSolar 2026: Volume Leaders Head-to-Head

    JA Solar vs JinkoSolar 2026: Volume Leaders Head-to-Head

    May 06, 2026
    Hoymiles vs APSystems 2026: Value Microinverter Platforms Compared

    Hoymiles vs APSystems 2026: Value Microinverter Platforms...

    May 05, 2026
    A large 100kW commercial-grade diesel standby generator enclosure installed outside a large estate home

    100 kW Cummins Home Generator Buyer's Guide: Specs, Insta...

    May 05, 2026
    Two home standby generators installed side by side for comparison

    Generac vs Kohler Home Standby Generators: 22–26kW Compared

    May 04, 2026
    Two commercial liquid-cooled standby generators side by side on a concrete pad

    Generac vs Cummins Commercial Standby: Liquid-Cooled 36–60kW

    Apr 29, 2026
    Generac vs Champion 2026: Premium vs Value Standby

    Generac vs Champion 2026: Premium vs Value Standby

    Apr 28, 2026

    Get Price Drops & Product Releases

    Weekly digest for installers and project managers — price drops, new stock, NEC code updates.

    PES Supply, a PES Global Group Company