SMA Solar Sunny Highpower Peak3 150kV String Inverter (SHP 150-US-20) | High-Efficiency Power Solution for Solar Projects

PES Supply, a PES Global Group Company
· 16 min read Reviewed by PES Supply editorial team
A large commercial string inverter station at a solar farm

Table of Contents

    SMA Sunny Highpower Peak3 150 (SHP 150-US-20): The Engineer's Guide to the 150kW, 1500V String Inverter

    Electrical design math, interconnection requirements, BOS economics, and field lessons for the inverter that anchors commercial solar blocks across North America.

    SMA Solar Sunny Highpower Peak3 (SHP 150-US-20) NEW PRODUCT 150KV 1500V String Inverter - 3-150-1500-2-20

    The string inverter beat the central inverter in commercial solar for one reason: granularity. When a 150kW string unit fails, you lose 150kW for a few days; when a 2MW central fails, you lose the plant for weeks while a tech drives out with a crate of IGBTs. The SMA Sunny Highpower Peak3 150 (SHP 150-US-20) is the current reference design for that argument — 150kW of 480V three-phase output on 1500V DC strings, built by the company that essentially invented the commercial string category. This guide covers what the spec sheet means in practice: the conductor and breaker math your electrician needs, the grid-support features your utility will ask about, production expectations by region, and the design patterns that separate a smooth commissioning from a red-tag.

    150kW
    AC output, 480V 3-phase
    1500V
    Max DC system voltage
    99%
    Peak conversion efficiency
    250A
    AC output breaker per NEC math

    Where the Peak3 150 Fits

    The SHP 150-US-20 is aimed at commercial rooftops from roughly 300kW up, carports, and ground-mount blocks that tile into the multi-megawatt range. Below that band, a wall of residential-class string inverters is usually cheaper; above it, you're comparing against SMA's larger PEAK3 FLEX variants and competing 250kW-plus units (our 250kW+ inverter collection maps that tier). SMA's 40-plus years of inverter manufacturing history — covered in our SMA brand guide — matter here mostly for bankability: lenders and utilities both keep SMA on their approved-vendor lists without argument, which shortens two of the longest poles in any commercial project schedule.

    There's also a portfolio-logic argument that rarely appears in spec sheets: standardizing on one inverter platform across multiple sites cuts the owner's spare-parts shelf, training burden, and monitoring fragmentation. A facility group running six buildings on one Peak3 profile has one grid-settings file, one alarm taxonomy, and one service relationship. Developers who mix inverter brands project by project save pennies on BOMs and spend dollars on operations for the next twenty years.

    If you're new to how string architecture differs from microinverter and central designs, our explainers on what a string inverter is and microinverters vs. string inverters lay out the tradeoffs before you commit a block design.

    Core Specifications and What They Mean

    Read the spec table below as a design document, not marketing: each row maps to a decision your engineer of record or your installer will make on this project.

    Specification Value Field Meaning
    Model SHP 150-US-20 UL 1741-SB / IEEE 1547 listed for U.S. interconnection
    Rated AC output 150 kW @ 480 VAC, 3-phase Standard commercial service voltage — no step-up transformer on 480V services
    Max DC input voltage 1500 V Long strings: 26–28 modern modules per string, fewer homeruns
    Peak efficiency Up to 99% CEC-weighted figures run slightly lower; still class-leading
    MPPT architecture Multiple independent trackers Tolerates mixed orientations and row-level shading without string-level compromise
    Grid support Rule 21 / IEEE 1547 smart-inverter functions Volt-VAR, frequency-watt, ramp control — the utility interconnection checklist
    Enclosure Outdoor-rated, commercial duty Pad or rack mount; no inverter room required
    Monitoring Sunny Portal / Data Manager integration Fleet-level analytics and automated fault notification
    Field note: I've commissioned Peak3-class SMA units on three commercial rooftops, and the feature that saves real money isn't efficiency — it's the onboard IV-curve diagnostic. On a 400kW school project, the inverter's own trace flagged a miswired string (two modules reversed in one row) in the first hour. On older gear we'd have burned half a day with a handheld tracer hunting that fault.

    Layout Tolerance: Why Multiple MPPTs Matter on Real Roofs

    Commercial roofs are never the clean rectangle the sales brochure assumes. Parapet shadows, HVAC clusters, skylight setbacks, and fire-code pathways carve every array into sub-arrays with different orientations and shade histories. A central inverter forces all of those into one maximum-power point — the worst-performing section drags the whole DC bus. The Peak3's multiple independent MPPT trackers let you assign each roof facet its own tracker, so a shaded southwest corner never taxes the clean south rows.

    The design discipline that pays: keep strings on a single MPPT within one orientation class and one tilt. Mixing a 10° tilt row with a 30° tilt row on the same tracker costs 2–4% of annual yield in our production data reviews — a silent loss that never appears as an alarm. When the roof forces a compromise, favor putting the compromised strings on their own tracker and leave the clean strings unmixed.

    Heat, Derating, and Siting the Units

    Every inverter derates when it gets hot; the Peak3 150 is no exception. Full 150kW output is available across a wide ambient band, but sustained ambient above roughly 45°C (113°F) begins to trim output, and the trim compounds if you mount units in direct western sun against a reflective parapet. The siting rules we apply on every project:

    • Shade the inverter, not just the array. A simple shade canopy over a row of inverters preserves several percent of summer-afternoon production in hot climates.
    • Respect airflow clearances. The convection path needs open space at intake and exhaust; boxing units into architectural screens without airflow engineering is the classic self-inflicted derate.
    • Altitude counts. Above ~2,000m, thinner air cools less effectively; apply the datasheet altitude derate rather than discovering it in July.
    • Dust and agriculture. On sites with heavy dust, chaff, or cottonwood seed, put filter checks on the quarterly maintenance list; clogged heatsink fins mimic a failing fan.

    Read efficiency claims in this light: the up-to-99% peak figure is real, but delivered annual efficiency is peak efficiency minus thermal derating, minus DC/AC clipping at your chosen oversize ratio, minus downtime. We model a DC/AC ratio of 1.25–1.35 on most Peak3 projects; the small midday clip cost is repaid by stronger morning, evening, and winter production on the fixed AC interconnection.

    The Economics Table: Block-Level BOS Comparison

    What does the architecture choice actually save on a representative 1MW DC block? Based on project budgets we've reviewed, the line-item pattern is consistent:

    Line Item (1MW DC block) Peak3 150 String Design Legacy 1000V String Design Delta Driver
    Inverter count 5–6 units 7–8 units Higher unit rating
    String count ~68 ~91 1500V vs 1000V ceiling
    PV homerun wire Baseline +25% Fewer, longer strings
    Combiner / recombiner hardware Minimal Moderate String-level landing at inverter
    AC switchgear 5–6 × 250A breakers 7–8 × smaller frames Unit count
    Install labor (electrical) Baseline +15–20% Terminations and trenching
    Annual service exposure Unit swap, local labor Unit swap, local labor Same service model, fewer units to visit

    Add those deltas and the 1500V Peak3 architecture typically lands 3–6% under a 1000V string design on total installed cost — before the production benefit of more granular MPPT tracking. On tight commercial margins, that delta is often the difference between a project that clears the investment committee and one that doesn't.

    Procurement Checklist for the Peak3 150

    SMA Solar Sunny Highpower Peak3 1500DC String Inverter - SHP 150-US-20

    1. Confirm the service voltage first. The -US-20 is a 480V unit; a 208V service changes the whole electrical design, so verify the utility service before you fall in love with a BOM.
    2. Lock the grid profile early. Request the utility's smart-inverter settings sheet during interconnection application, not after equipment arrives.
    3. Order with the monitoring bundle. Data Manager or gateway hardware has its own lead time; a missing gateway delays permission-to-operate as surely as a missing inverter.
    4. Stage spare fuses and fans. Wear items on the shelf turn a two-day outage into a two-hour one.
    5. Verify racking/pad drawings. Confirm weight, clearance, and conduit entry locations against the current installation manual revision.
    6. Schedule the witness test window. Utility witness availability, not equipment, sets the final schedule more often than any other factor.

    AC-Side Design: Breaker and Conductor Math (NEC 240.6 / 310.16)

    The Peak3 150's nameplate output determines its entire AC interconnect. Working the numbers per NEC 690.8 (inverter output circuits sized at 125% of continuous output current):

    Design Step Calculation Result
    Rated output current 150,000 W ÷ (480 V × √3) 180.4 A
    Continuous-load factor (NEC 690.8(B)/210.19) 180.4 A × 1.25 225.5 A
    Overcurrent device (NEC 240.6 standard sizes) Next standard size up 250 A breaker
    Conductor, copper, 75°C terminations (NEC 310.16) ≥ 225.5 A ampacity 250 kcmil Cu (255 A)
    Conductor, aluminum, 75°C (budget option) ≥ 225.5 A ampacity 350 kcmil Al (230 A)
    Equipment grounding conductor (NEC 250.122, 250A OCPD) Per table 4 AWG Cu minimum

    Two practical notes on that table. First, the 250A feeder is why the Peak3 150 pairs naturally with 480V services: at 208V the same 150kW would demand 416A before the 125% factor — a 600A frame breaker and parallel 500 kcmil runs, which is exactly why the 208V variant of large string inverters costs more to install even when the unit price is identical. Second, voltage drop on long runs: keep the inverter within a few hundred feet of the switchgear or run the drop calculation; at 180A, every extra 100 feet of 250 kcmil copper costs you roughly 0.7% of delivered energy.

    DC-Side Design: 1500V String Economics

    The 1500V ceiling is the Peak3's biggest balance-of-system lever, and it changes the geometry of the whole DC plant. Longer strings mean fewer strings, and fewer strings mean less of everything downstream — trenching, wire, combiner inputs, and labor hours. With modern 550–600W bifacial modules (Voc ≈ 50V, corrected per NEC 690.7 for your design low), the string-length math lands here:

    Design Low Temp Corrected Module Voc Max Modules / String String Power (550W modules)
    −5°C 53.8 V 27 14.85 kW
    −15°C 55.0 V 27 14.85 kW
    −25°C 56.3 V 26 14.30 kW
    −35°C 57.6 V 26 14.30 kW

    At 26–27 modules per string, a 1MW DC block needs roughly 67–70 strings. On 1000V gear with 20-module strings, the same block needs ~91 strings — about 25% more homerun cable, 25% more trench feet, and 25% more terminations to torque and inspect. That delta is where the 1500V architecture pays for itself, and it's why our commercial solar panels guide and the commercial installation cost breakdown both treat DC system voltage as a first-order cost variable rather than a footnote in the equipment schedule.

    Field note: We pulled the homerun schedule on a 1.2MW ground-mount last year and the 1500V design saved 18,000 feet of PV wire versus the 1000V alternative the owner had budgeted. At copper prices that spring, the wire delta alone covered the engineering redesign fee with money left over. I always tell developers: before you value-engineer the inverter line, value-engineer the string length.

    Grid Support and Interconnection: What the Utility Will Ask

    Modern interconnection agreements read like firmware spec sheets. The Peak3 150 ships with the smart-inverter function set that Rule 21 and IEEE 1547-2018 jurisdictions require, and understanding the vocabulary saves weeks in the interconnection queue:

    • Volt-VAR (Q(U)): The inverter absorbs or injects reactive power to hold grid voltage. Utilities in Hawaii, California, and increasingly the Midwest mandate specific curves; the Peak3's are field-configurable.
    • Frequency-Watt: Automatic power curtailment during over-frequency events, replacing the old trip-and-disconnect behavior that destabilized grids with high solar penetration.
    • Ramp-rate control: Limits how fast output changes — the function that keeps cloud-edge transients from tripping feeder protection.
    • Anti-islanding: IEEE 1547-mandated detection and cease-energization behavior; certified out of the box under UL 1741-SB.
    • Export limiting: Configurable zero-export or capped-export operation for non-export and NEM-capped interconnections.

    For three-phase service fundamentals — wye vs. delta, phase balancing, and why 480V wye is the friendliest interconnection — see our three-phase power explainer.

    Peak3 150 vs. the Alternatives

    Criterion SMA Peak3 150 (150kW string) Central Inverter (1–4MW) Residential-Class String Wall
    Failure impact 150kW offline Entire plant offline 10–20kW offline
    Service model Swap unit; local labor Factory tech, parts lead time Swap unit; local labor
    DC voltage 1500V 1500V 600–1000V
    Granularity of MPPT Multiple per 150kW Minimal Maximum
    Install cost per kW (typical block) Low Lowest at multi-MW scale High above ~500kW
    Best fit 300kW–10MW commercial/utility blocks 10MW+ utility plants Under ~300kW

    For buyers cross-shopping the 100kW tier as well, our 100kW inverter guide and the 100kW inverter collection bracket the Peak3 150 from below, while the 150kW inverter collection shows its direct peer set. The broader technology arc — how string inverters absorbed features that used to require central stations — is covered in our inverter technology evolution retrospective.

    Production Modeling: What 150kW Delivers in a Year

    Owners sign for kilowatt-hours, not kilowatts. At a 1.3 DC/AC ratio, each Peak3 150 carries about 195kW DC of array. Annual production then tracks regional irradiance; the planning numbers below assume a well-designed fixed-tilt array with standard loss factors:

    1. Enhanced Energy Yield

    Region (Representative City) Specific Yield (kWh/kWp/yr) Annual Energy per 195kW DC Inverter Block Revenue Equivalent @ $0.12/kWh
    Southwest (Phoenix) ~1,750 ~341,000 kWh ~$40,900
    South Central (Dallas) ~1,550 ~302,000 kWh ~$36,300
    Southeast (Atlanta) ~1,450 ~283,000 kWh ~$33,900
    Mid-Atlantic (Philadelphia) ~1,300 ~254,000 kWh ~$30,400
    Pacific Northwest (Seattle) ~1,100 ~215,000 kWh ~$25,700

    Those per-unit numbers are why block-level decisions compound: a 2% tracking or thermal improvement on a ten-unit Peak3 plant in Dallas is worth roughly 60,000kWh — about $7,200 — every year for the life of the system. Sweat the MPPT assignments, the shade canopy, and the airflow clearances; the revenue meter notices all of them.

    Commissioning and Operations

    Commissioning a Peak3 block follows a disciplined sequence: verify string polarity and open-circuit voltage against the design schedule before landing any homerun, torque all DC terminations to spec, energize strings one MPPT at a time while watching the inverter's insulation-resistance self-test, then configure the grid profile to match the interconnection agreement exactly — not approximately. An incorrect volt-VAR curve is the most common cause of failed witness tests, and it's a five-minute parameter fix if you catch it before the utility witness arrives.

    Two more commissioning habits separate clean handovers from punch-list purgatory. First, photograph every DC landing with the string label visible before closing covers — when a string underperforms in month four, that photo answers whether the problem is in the field or the wiring. Second, baseline the IV curves at commissioning while the array is clean and new; every future trace then has an honest reference, and degradation conversations with the module vendor start from evidence instead of argument.

    In operation, the Sunny Portal / Data Manager integration does the heavy lifting: automated yield-vs-expected reporting, fault notification, and the IV-curve diagnostics that catch soiling patterns and connector degradation before they show up in the revenue meter. Budget the monitoring subscription in the pro forma; on commercial plants it pays for itself the first time it catches a downed string in week one instead of month three.

    Set the alert thresholds aggressively at first — every 1% of unexpected underperformance — and then relax them once you know the plant's personality. New arrays produce plenty of benign alerts (soiling after pollen season, snow days, utility voltage excursions), and operators who tune alerts to the plant's real baseline respond to the ones that matter. The monitoring data also feeds the asset's resale value: a documented production history with clean variance logs is worth real money when a building trades or a portfolio refinances.

    Field note: I tell every facility manager the same thing at handover: put the monitoring alert email in front of a human who can act on it. We found a failed cooling fan on one unit because the alert went to a former employee's inbox for six weeks — production loss was small, but the fan is a wear item and the catch should have been same-week. The hardware is reliable; the alert routing is where operations actually fail.

    Frequently Asked Questions

    What size breaker and wire does the SHP 150-US-20 require?

    At 480V three-phase, rated output current is 180.4A. NEC 690.8's 125% continuous factor brings that to 225.5A, so the design uses a 250A breaker (NEC 240.6 standard size) with 250 kcmil copper conductors at 75°C per NEC Table 310.16, or 350 kcmil aluminum as a budget alternative.

    How many solar panels can I connect per string?

    With modern 550W-class modules (Voc ≈ 50V) corrected per NEC 690.7, you can run 27 modules per string down to about −15°C design low, and 26 modules to −35°C — roughly 14.3–14.9kW per string. Always verify against the specific module's Voc temperature coefficient.

    Can the Peak3 150 interconnect at 208V?

    The SHP 150-US-20 is a 480V machine. At 208V services you'd either specify the 208V-rated variant or accept the transformer cost — and at 150kW, the 208V current (416A before the 125% factor) usually makes the 480V path cheaper overall.

    Does the Peak3 meet California Rule 21 and IEEE 1547-2018?

    Yes. The unit is UL 1741-SB listed with configurable volt-VAR, frequency-watt, ramp-rate control, and anti-islanding functions. The grid profile is set during commissioning to match your interconnection agreement.

    What happens when one unit fails in a multi-inverter block?

    Only that 150kW of capacity goes offline. The unit is designed for swap-out service with standard electrical labor — a key economic advantage over central inverters, where a single failure can idle an entire multi-megawatt plant for weeks.

    Is the Peak3 150 suitable for small commercial buildings?

    Generally no — its sweet spot starts around 300kW of array. Below that threshold, multiple smaller string inverters usually install cheaper, match fragmented roof layouts more flexibly, and keep service calls proportionally simpler.

    What DC/AC ratio should I design to?

    Most Peak3 projects model well at 1.25–1.35 DC/AC. The modest midday clipping in peak summer is repaid by stronger morning, evening, and winter production on a fixed AC interconnection, and the extra DC capacity is usually the cheapest energy in the entire system design.

    Specifying a commercial block? We stock the SMA Sunny Highpower Peak3 150 and the full SMA commercial line, including the Peak3 125 for smaller services. Call 866-607-3636 for project pricing, datasheets, and string-design support.

    Need Help Sizing This?

    Our team can help you calculate loads, select the right equipment, and source everything from one PO.

    📞 (502) 790-0600

    Email Our Team
    Solar Panels Generators Batteries / ESS EV Chargers Circuit Breakers Charge Controllers

    One PO. One Invoice. Every Trade Covered.

    PES Supply is the distribution arm of PES Global Group — 50,000+ SKUs from 169 authorized brands, LTL freight shipping from Louisville, KY.

    Get a Quote
    Share: X f in @

    Related Articles

    EPA Section 608 certification exam types and passing scores chart — PES Supply

    EPA Section 608 Certification: Complete Study Guide (Type...

    Aug 30, 2026

    R-410A Phase-Down 2026: What HVAC Contractors Need to Know

    Aug 29, 2026
    N-Type vs TOPCon vs HJT Solar Panels: Which Technology Is Best in 2026?

    N-Type vs TOPCon vs HJT Solar Panels: Which Technology Is...

    Aug 26, 2026
    How Many Solar Panels Do I Need for 10,000 kWh Per Month? - The Complete 2026 Guide

    How Many Solar Panels Do I Need for 10,000 kWh Per Month?...

    Aug 26, 2026
    Solar + Battery Storage: The Complete 2026 Guide for Homeowners

    Solar + Battery Storage: The Complete 2026 Guide for Home...

    Aug 24, 2026
    Commercial rooftop solar panels at sunset with American flag — ITC safe harbor and commence-construction rules for 2026

    ITC Safe Harbor & Commence-Construction: What Solar Buyer...

    Aug 17, 2026
    Solar panel modules stacked at a U.S. port facility with customs documentation overlay, representing Section 232 tariff compliance for solar imports

    Section 232 Solar Tariffs & Minimum Import Prices: The De...

    Aug 14, 2026
    Close-up of an electrical breaker panel with a licensed electrician testing circuits with a multimeter

    How to Size Circuit Breakers: NEC 125% Rule (2026)

    Aug 12, 2026
    Container port at golden hour with crane lifting crated solar panels over the dock

    Solar Module Sourcing in 2026: Regional Costs, Tariff Sta...

    Aug 09, 2026
    Pallets of stacked solar modules in a bright distribution warehouse with forklift and conduit racks

    Module Prices Hit $0.34/W — So Why Did Your Commercial Qu...

    Aug 08, 2026
    Two installers finishing a residential rooftop solar installation at sunset

    The Safe Harbor Deadline Passed. Here's What Actually Hap...

    Aug 07, 2026
    Worker in cleanroom suit inspecting a silicon ingot at a solar polysilicon factory, shipping containers beyond the window

    Section 232 Polysilicon Tariffs Hit Solar: What August 20...

    Aug 06, 2026
    Technician's hands with clipboard and tablet inspecting a home standby generator, shallow depth of field

    Generac Generator Warranty Explained: 5, 7, and 10-Year E...

    Aug 03, 2026
    Residential standby generator installed beside a modern suburban home's electrical service panel at golden hour

    Whole Home Generator Sizing Guide 2026: How Many kW Do Yo...

    Aug 03, 2026
    Wall-mounted home battery storage unit installed in a garage beside a solar inverter

    Battery Storage Incentives by State: 2026 Rebate Programs...

    Jul 30, 2026
    Rows of solar panels in a distribution warehouse, tied to 2026 supply and pricing trends

    Solar Market Outlook H2 2026: Panel Prices, Supply Chain,...

    Jul 29, 2026
    Imported solar panels in shipping crates at a port, subject of 2026 tariff updates

    Solar Industry Tariff Updates: What Installers Need to Kn...

    Jul 27, 2026
    A city skyline at dusk with glowing windows and power transmission lines in the foreground

    Growing Electricity Demand: Why Energy Policy Reform Is M...

    Jul 24, 2026
    A technician installing a wall-mounted mini-split heat pump indoor unit in a bright modern living room

    Mini Split Installation Cost (2026): Equipment, Labor & E...

    Jul 23, 2026
    Solar panels elevated over green farmland with sheep grazing beneath

    Harnessing the Sun and Soil: How Agrivoltaics is Revoluti...

    Jul 21, 2026
    A showroom display of several brand-new black solar panel models angled on stands

    Newest Solar Panels in 2026: Latest Models from Leading U...

    Jul 18, 2026
    From the Field: A Master Electrician's Guide to Solar Commissioning

    From the Field: A Master Electrician's Guide to Solar Com...

    Jul 15, 2026
    A home energy storage system with a smart meter showing zero grid flow

    How Can a Residential ESS Achieve 0W Grid Flow?

    Jul 14, 2026
    Close-up of an automatic transfer switch panel with conduit in a residential utility room

    How Automatic Transfer Switches Work

    Jul 12, 2026
    A large residential rooftop fully covered with solar panels on a sunny day

    Solar Panels for 10,000 kWh/Month: 2026 Sizing Guide

    Jul 06, 2026
    7 Benefits of Switching to Commercial Solar Energy

    7 Benefits of Switching to Commercial Solar Energy

    Jun 30, 2026
    2026 H1 Solar Industry Recap: Record Installations, Tariff Uncertainty, and Storage Dominance

    2026 H1 Solar Industry Recap: Record Installations, Tarif...

    Jun 30, 2026
    How to Successfully Implement Solar Energy in Your Business

    How to Successfully Implement Solar Energy in Your Business

    Jun 30, 2026
    Three different solar panel types displayed side by side on stands outdoors

    The Main Types of Solar Panels: Which Should You Choose?

    Jun 26, 2026
    After Nearly 20 Years, America's Biggest Clean Energy Project Is Finally Operational

    America's Largest Clean Energy Project Goes Live After Ne...

    Jun 26, 2026
    Procurement Strategy: How to Navigate Solar Equipment Sourcing in 2026

    Procurement Strategy: How to Navigate Solar Equipment Sou...

    Jun 15, 2026
    A friendly solar consultant shaking hands with a homeowner on a sunny driveway

    How to Find Local Solar Companies Near Me

    Jun 14, 2026
    How Long Do Solar Panels Last? (2026 Guide)

    How Long Do Solar Panels Last? (2026 Guide)

    Jun 14, 2026
    A homeowner in conversation with a solar consultant on a sunny driveway

    What Questions Should I Ask My Solar Company?

    Jun 14, 2026
    A homeowner on the porch of a solar-equipped suburban home reviewing an energy bill

    Is Solar Worth It for My Home?

    Jun 10, 2026
    A homeowner and contractor reviewing permit paperwork on a clipboard in front of a house with new solar panels

    What Are Solar Permits and How Long Do They Take?

    Jun 07, 2026
    A homeowner at a kitchen table with a calculator and solar quotes

    Solar Panel Cost in 2026: What You'll Actually Pay

    Jun 06, 2026
    How Much Money Can I Save With Solar Panels?

    Solar Panel Savings in 2026: Real Numbers by State

    May 30, 2026
    The New York State Capitol area skyline with rooftop solar installations in the foreground

    New York Boosts Solar Investment in 2027 State Budget

    May 29, 2026
    A compact modular microinverter unit being mounted beneath rooftop solar panels by an installer

    Mango Power modular microinverter hits US residential sol...

    May 29, 2026
    A futuristic solar panel manufacturing facility with robotic arms and rows of new modules

    How Tesla Plans to Scale Solar Production to 100GW by 2028

    May 25, 2026
    A vast Australian solar farm with rows of panels and large battery storage containers

    NSW Seeks 2.5 GW Renewable Capacity, 12 GWh Storage Under...

    May 21, 2026
    Solar Workforce Crisis 2026: Installer Shortage, Training Programs, and Electrician Demand

    Solar Workforce Crisis 2026: Installer Shortage, Training...

    May 15, 2026
    Cows grazing in a green alpine pasture beneath elevated solar panels

    Nestlé Launches Agri-PV “Cow Solar” Project in Allgäu, Bl...

    May 04, 2026
    A row of suburban homes with rooftop solar and small battery cabinets

    FranklinWH Systems to Launch First U.S. City-Owned Reside...

    May 01, 2026
    Three sleek white home battery units wall-mounted in a row in a modern garage

    Tesla Expands Energy Solutions with Three-Phase Powerwall 3P

    Apr 26, 2026
    Solar panel canopies over a California school campus parking lot

    School District in California Deploys 3.1 MW Solar System...

    Apr 14, 2026
    The Future of Solar: 7 Breakthrough Technology Trends in 2026 — Portlandia Electric Supply

    The Future of Solar: 7 Breakthrough Technology Trends in ...

    Apr 12, 2026
    Trainees in safety vests learning solar panel installation at a training facility

    New York Boosts Renewable Workforce Funding with $50 Mill...

    Apr 05, 2026
    Pallets of wholesale solar panels stacked in a warehouse for EPC and installer buyers

    Wholesale Solar Panels: The Complete B2B Procurement Guid...

    Mar 13, 2026

    Get Price Drops & Product Releases

    Weekly digest for installers and project managers — price drops, new stock, NEC code updates.

    PES Supply, a PES Global Group Company