Solar Interconnection Backlog Crisis 2025: Grid Constraints Delaying Projects Nationwide

PES Supply, a PES Global Group Company
· 16 min read Reviewed by PES Supply editorial team
Solar Interconnection Backlog Crisis 2025: Grid Constraints Delaying Projects Nationwide

Table of Contents

    Last Updated: 2026 • Sources: LBNL "Queued Up" reports, FERC Orders 2023/2023-A, ISO/RTO public filings and status reports

    The US solar industry's biggest bottleneck in 2025 wasn't modules, inverters, labor, or capital. It was a queue. More than 2,600 gigawatts of proposed generation and storage sat in interconnection queues waiting for grid studies — more than double the capacity of the entire existing US power plant fleet. Projects that used to clear interconnection in under two years were routinely waiting four, five, or six. Every year of queue time is carrying cost, option payments, and PPA price inflation — and for a growing share of projects, it's the difference between getting built and getting withdrawn.

    We live downstream of this backlog. When a developer's interconnection agreement finally lands, the equipment order that follows is a sprint — and the projects that survive the queue are the ones whose sponsors planned procurement around the wait instead of pretending it away. This guide maps the crisis as it actually stood in 2025–2026: the numbers, FERC Order 2023's reform architecture, how each ISO/RTO was actually performing, what cost allocation does to project math, and the strategies separating projects that energize from projects that expire.

    ⚡ Quick Answer

    The US interconnection backlog held roughly 2,600 GW of active requests at the end of 2023 — 95% of it solar, storage, and wind — against an installed national fleet of about 1,280 GW. Typical projects built in 2023 waited ~5 years from queue entry to operation, and historically fewer than 20% of queued projects ever reach commercial operation. FERC Order 2023 (effective November 2023) replaced serial studies with first-ready, first-served cluster studies, added financial readiness deposits and study-delay penalties. By 2025–2026, results diverged sharply by region: ISO-NE essentially cleared its backlog, PJM cut its queue ~60%, and MISO/NYISO/CAISO pushed through cluster and expedited-study reforms.

    The Scale of the Backlog: 2,600 GW and Counting

    Lawrence Berkeley National Laboratory's "Queued Up" research series is the definitive scoreboard, and its end-of-2023 dataset captured the system at maximum strain: 11,597 active projects representing 2.6 TW of generation and storage across the seven organized markets plus 44 non-RTO utilities. For every project that had ever made it through the queues to commercial operation since 2000 (~4,155 projects), nearly three had withdrawn along the way (~17,873). That withdrawal count isn't a footnote — it's the system's immune response to a process that had become unplannable.

    Metric Value Source / Note
    Active capacity in queues (end 2023) ~2,600 GW (2.6 TW) LBNL Queued Up
    Total installed US fleet ~1,280 GW LBNL — queues were 2× the existing fleet
    Solar + storage + wind share of queue 95% LBNL
    Solar capacity in queues 1,000+ GW LBNL / Utility Dive
    Battery storage in queues 1,000+ GW LBNL / Utility Dive
    Typical wait, projects built 2023 ~5 years queue-to-operation LBNL
    Historical completion rate (since 2000) <20% LBNL / Canary Media
    Capacity joining queues post-IRA (2022–2023) 1.2+ TW (540 GW storage, 500 GW solar, 125 GW wind) Utility Dive

    Digest the last row. The Inflation Reduction Act did exactly what it was designed to do — it made a terawatt of projects financially viable. But the queue infrastructure those projects had to pass through was designed in an era of dozens of requests a year, not thousands. Policy pulled demand forward into a process with no capacity to absorb it. That's the crisis in one sentence, and everything else in this article is detail.

    How the Queue Got This Bad

    The interconnection process was engineered for a twentieth-century grid: a few dozen large, dispatchable power plants per year, each studied individually against a stable load forecast. Three forces broke that design simultaneously. First, the cost collapse — solar, wind, and storage became the cheapest new capacity in most of the country, and development went from a utility-scale trickle to a flood of thousands of projects. Second, the policy accelerant — state RPS targets, corporate procurement, and then the IRA's 2022 credits made marginal projects financeable, and every one of them filed for interconnection. Third, the process itself — serial first-come-first-served studies meant every restudy cascaded: when project #47 in line withdrew, projects #48 through #200 often needed re-analysis, and queue positions became speculative assets held by developers with no intention of building.

    The result was a queue that measured itself in terawatts while the construction industry downstream of it measures itself in tens of gigawatts a year. Everyone who touched the system — developers, utilities, RTOs, equipment suppliers, financiers — knew by 2021 that the queue had stopped being a list of future power plants and had become a parking lot. Order 2023 is, at bottom, the formal admission of that fact: readiness deposits exist to evict the parked cars, cluster studies exist to clear the rest in batches instead of one restudy at a time.

    FERC Order 2023: The Reform Framework

    On July 28, 2023, FERC issued Order No. 2023 — the most comprehensive interconnection reform in two decades. Effective November 6, 2023, with compliance filings due April 3, 2024 (and clarifications following in Order 2023-A, March 2024), the rule rebuilt the queue around three pillars:

    Pillar What It Replaced What It Requires
    First-ready, first-served cluster studies Serial "first-come, first-served" studies of individual projects Transmission providers study validated projects in clusters, allocating network upgrade costs across the group
    Speed and accountability "Reasonable efforts" standard with no consequences for missed deadlines Enforceable study deadlines with penalty provisions; uniform affected-system modeling
    Technology and flexibility Rigid one-facility-per-request treatment Co-location of multiple facilities behind one point of interconnection; adding capacity without automatic material modification; storage and grid-enhancing tech accommodation

    The cluster process runs on gates and money: a defined cluster request window, a cure period for fixing deficient applications, and — the teeth of the reform — commercial readiness deposits in cash, letters of credit, or surety bonds, escalating as a project advances. Speculative projects that used to camp in the queue for free now pay to stay. That single change is why queue composition started cleaning up: when holding a queue position costs real money, only real projects hold positions.

    We've heard the grumbling from smaller developers about deposit requirements, and it's not wrong — readiness capital is a barrier that favors the well-funded. But the alternative was a queue where a serious project sat behind forty paper projects, and everyone in that line paid the carrying costs. Order 2023 chose the devil that at least moves.

    ISO/RTO Implementation: The 2025–2026 Scorecard

    Reform on paper is not reform in the field. By 2025–2026, each grid operator's Order 2023 transition had produced genuinely different outcomes — and for developers choosing where to site the next project, the regional divergence is now a site-selection variable as real as irradiance.

    ISO/RTO Key 2025–2026 Developments Status
    PJM Backlog cut ~60%; ~50 GW cleared through study process; 47 GW with completed interconnection process free to build; 18 GW via "Fast Lane"; 51 projects / 9.3 GW selected in Reliability Resource Initiative (May 2025); Expedited Interconnection Track accepted by FERC (June 2026); new Cycle process launching spring 2026 Transition period nearly complete; AI-assisted planning tools in deployment with Google/Tapestry
    ISO-NE Completed Order 2023 compliance; queue described as "essentially with no backlog" Best-performing region; pursuing large-load reforms (BYONG) with rules expected 2027
    MISO Expedited Resource Addition Study (ERAS) filed June 2025, FERC-accepted July 21, 2025; 40 projects / 19 GW completed ERAS by mid-2026; Zero Injection Generator Interconnection Agreement (ZGIA) in development Addressing cited 4.7 GW resource adequacy shortfall by 2028
    NYISO Cluster Study Process adopted; 89 completed projects / 11+ GW awaiting commercial operation; Transition Cluster at 91 projects / 15+ GW Next cluster window scheduled July 31, 2026
    CAISO Cluster 15 Queue Report published December 2025; continuing cluster processing Ongoing; transmission planning strain from data-center and electrification load growth

    Two stories stand out. ISO-NE demonstrated that a region with modest queue volume and aggressive compliance can actually finish the job — proof the Order 2023 architecture works when the inputs are manageable. And PJM, carrying the largest queue in the country, showed that scale plus automation plus enforcement can cut a backlog by more than half in two years. The lesson transfers: the regions still drowning are mostly the ones whose load growth (looking at you, data centers) is refilling the queue as fast as reform drains it.

    Cost Allocation: Where Projects Live or Die

    The least understood part of interconnection is the part that kills the most projects: network upgrade cost allocation. When a cluster study determines that your project requires transmission upgrades — a reconductored line, a new substation, reactive compensation — the cluster assigns those costs to the projects causing them. The number lands late in the process, and it can move a project's economics by more than every module price swing of the last five years combined.

    Scenario (200 MW solar project) Math Impact
    Clean interconnection Minimal upgrades: $10M ÷ 200,000 kW $50/kW ≈ +4% on a ~$1,200/kW build — financeable
    Moderate upgrades Substation + reconductor: $40M ÷ 200,000 kW $200/kW ≈ +17% capex — PPA price renegotiation territory
    Heavy network upgrades Line rebuild + reactive support: $100M ÷ 200,000 kW $500/kW ≈ +42% capex — most projects withdraw here

    That third row is the queue's mortality mechanism. A developer spends two to four years and seven figures on studies, land, and deposits, then receives an upgrade assignment that adds 40% to capex — and withdraws. The withdrawal frees the capacity for the next cluster, which is exactly what Order 2023 intends: capital and grid capacity recycle toward projects that pencil. Painful for the individual sponsor; healthy for the system. If you're evaluating queue positions today, the single best due-diligence dollar you can spend is on early power-flow screening of candidate points of interconnection before you commit site control money.

    What Surviving Projects Do Differently

    Watching projects move through — and die in — these queues for years, a clear pattern separates the energizers from the withdrawals:

    • They screen before they queue. Serious developers run independent power-flow and short-circuit analysis on candidate POIs before filing, targeting substations with headroom instead of famous transmission corridors everyone else is also crowding.
    • They bring storage or go hybrid. Solar-plus-storage projects that can shape output around constraints clear studies more cleanly than standalone solar in saturated zones — and the IRA's standalone storage credit made the storage leg financeable on its own.
    • They treat deposits as portfolio decisions. Readiness deposits at multiple POIs is expensive; readiness deposits at multiple screened POIs is a strategy.
    • They plan procurement around the queue, not against it. Long-lead electrical gear — transformers, switchgear, breakers — gets spec'd and reserved early against the expected energization window, with safe-harbor tax strategy aligned to the same dates. When the interconnection agreement lands, the schedule sprint is won or lost on equipment lead times.
    • They communicate honestly with offtakers. PPAs with queue-delay provisions survive; PPAs that pretend 5-year waits don't exist end up in renegotiation.

    From the supply side: the pattern we see is consistent — projects that emerge from the queue with a fighting chance are the ones whose teams called us about transformer and switchgear lead times before the interconnection agreement, not after. A 50-week transformer lead time against a 12-month construction window is a schedule you fix at procurement, not at commissioning. If your project is approaching an IA, start the equipment conversation now.

    The Equipment Side: What Queue Delays Do to Procurement

    Every year a project sits in the queue, its procurement plan ages. Module prices fall (good), electrical gear lead times stretch (bad), and the tax-credit clock keeps ticking (urgent). The projects that handle this best treat the queue window as procurement runway:

    Equipment Typical Lead Time Reality Queue-Aware Strategy
    Power transformers / GSU 50–100+ weeks for large units Reserve production slots at IA milestone; the single longest pole in most schedules
    Medium-voltage switchgear 30–60 weeks Spec and order against expected energization, with penalty-aware delivery clauses
    Modules Weeks to months; prices volatile Delay commitment where safe-harbor rules allow; falling prices reward patience
    Inverters / storage 8–24 weeks typical Lock firmware-compatible SKUs at engineering freeze; re-verify listings before energization
    Breakers / BOS Days to weeks at distribution Commodity — but a missing $400 breaker still holds a COD hostage

    The safe-harbor dimension deserves emphasis: under the commence-construction rules, incurring at least 5% of project cost in the right tax year can lock credit treatment — which turns early equipment purchases from a schedule risk into a tax strategy. Our safe-harbor guide covers the mechanics. The dangerous version is buying hardware for a queue position that later dies; the smart version is safe-harboring with transferable, resale-friendly equipment classes rather than project-specific custom gear.

    We've been on both ends of this. We've rushed a transformer order for a developer whose IA landed nine months early (rare, happy day), and we've warehoused switchgear for a project whose cluster study slid twice. The difference in outcomes was never luck — it was whether the contract had delivery-flexibility clauses written for a queue world.

    The Outlook: Is the Crisis Actually Ending?

    Honest answer: the backlog as a process failure is improving; the backlog as a capacity constraint is not. Order 2023's machinery — cluster studies, deposits, penalties — is demonstrably draining speculative volume, as ISO-NE and PJM prove. But two forces keep refilling the pipe. First, load growth: data centers, electrification, and industrial reshoring are pulling new generation demand forward faster than transmission gets built, and interconnection queues ultimately surface the transmission system's limits, not just its paperwork. Second, the transmission build-out itself: queues clear faster when the network has headroom, and transmission permitting remains the slower crisis behind this one.

    The 2025–2026 retrospectives capture the split well — see our 2025 H2 industry retrospective for the market context, the 2025 consolidation analysis for what queue stress did to developer balance sheets, and the 2026 workforce analysis for the labor side of actually building what clears the queue. For tax-timing strategy on projects approaching energization, our safe-harbor and commence-construction guide is the operative reference.

    Our read from the equipment desk: plan for a world where interconnection is the pacing item through the rest of the decade. Reform will keep shaving the administrative half of the delay, but the physical half — transmission headroom — only moves as fast as steel gets strung. The winners in this environment are the developers who site where the grid has room, the contractors who can mobilize the moment an IA signs, and the suppliers who keep long-lead gear honest. The queue crisis isn't ending; it's becoming a discipline.

    Frequently Asked Questions

    How big is the US solar interconnection backlog?

    At the end of 2023, active interconnection requests totaled roughly 2,600 GW across 11,597 projects — more than double the ~1,280 GW installed US power plant fleet. Solar, storage, and wind made up 95% of queued capacity, with solar and battery storage each exceeding 1,000 GW. Over 1.2 TW joined the queues in the two years following the Inflation Reduction Act.

    How long does interconnection take in 2025–2026?

    Projects that reached operation in 2023 waited roughly five years from queue entry on average, per LBNL data. Under FERC Order 2023's cluster-study reforms, timelines are improving in leading regions — ISO-NE has essentially cleared its backlog, and PJM's new Cycle process targets one-to-two-year study timelines — but results vary sharply by ISO/RTO and by the condition of the local transmission system.

    What is FERC Order 2023?

    Issued July 28, 2023 and effective November 6, 2023, Order 2023 is FERC's comprehensive interconnection reform. It replaces serial first-come-first-served studies with first-ready, first-served cluster studies; imposes enforceable study deadlines with penalties; requires escalating commercial-readiness deposits to enter and remain in the queue; and accommodates co-location, storage, and surplus interconnection service. Order 2023-A (March 2024) added clarifications.

    What percentage of queued projects actually get built?

    Historically fewer than 20%. LBNL's data shows about 17,873 projects withdrew from queues against roughly 4,155 that reached commercial operation since 2000. Most withdrawals follow network-upgrade cost assignments that break project economics — which is by design under the reformed process, as capacity recycles to financeable projects.

    Which grid region has the shortest interconnection wait?

    As of 2025–2026, ISO New England reported the strongest position, having completed Order 2023 compliance with essentially no remaining backlog. PJM reduced its backlog about 60% and launched expedited tracks for reliability-valuable projects. MISO's one-time ERAS process cleared 40 projects totaling 19 GW by mid-2026. Wait times remain highly site-specific within every region.

    What can developers do to survive the interconnection queue?

    Screen candidate points of interconnection with independent power-flow analysis before filing; consider hybrid solar-plus-storage configurations that clear studies more cleanly in saturated zones; treat readiness deposits as a portfolio strategy across multiple screened POIs; reserve long-lead equipment (transformers, switchgear) against the expected energization window; and align safe-harbor tax strategy with queue timelines so credit eligibility survives the wait.

    Queue-Approved? Now Beat the Equipment Clock.

    Transformers, switchgear, inverters, storage, and full BOS — 50,000+ SKUs from 169 authorized brands with nationwide LTL freight from Louisville, KY. Start procurement before the IA lands.

    Shop Solar Equipment  Request a Project Quote

    About PES Supply

    PES Supply is a nationwide distributor of Tier 1 solar panels, inverters, battery storage, switchgear, transformers, racking, and complete electrical project kits — 50,000+ SKUs across 169 authorized brands with full OEM warranties and nationwide LTL freight from our Louisville, Kentucky supply house. Phone: 1-888-876-0007portlandiaelectric.supply

    Sources: LBNL "Queued Up" reports; FERC Orders 2023 and 2023-A; PJM, ISO-NE, MISO, NYISO, and CAISO public status reports; Utility Dive; Canary Media.

    Disclaimer: Queue statistics and ISO/RTO status change continuously. Figures cited reflect the most recent public reporting at the time of writing and may have been superseded.

    Need Help Sizing This?

    Our team can help you calculate loads, select the right equipment, and source everything from one PO.

    📞 (502) 790-0600

    Email Our Team
    Solar Panels Generators Batteries / ESS EV Chargers Circuit Breakers Charge Controllers

    One PO. One Invoice. Every Trade Covered.

    PES Supply is the distribution arm of PES Global Group — 50,000+ SKUs from 169 authorized brands, LTL freight shipping from Louisville, KY.

    Get a Quote
    Share: X f in @

    Related Articles

    EPA Section 608 certification exam types and passing scores chart — PES Supply

    EPA Section 608 Certification: Complete Study Guide (Type...

    Aug 30, 2026

    R-410A Phase-Down 2026: What HVAC Contractors Need to Know

    Aug 29, 2026
    N-Type vs TOPCon vs HJT Solar Panels: Which Technology Is Best in 2026?

    N-Type vs TOPCon vs HJT Solar Panels: Which Technology Is...

    Aug 26, 2026
    How Many Solar Panels Do I Need for 10,000 kWh Per Month? - The Complete 2026 Guide

    How Many Solar Panels Do I Need for 10,000 kWh Per Month?...

    Aug 26, 2026
    Solar + Battery Storage: The Complete 2026 Guide for Homeowners

    Solar + Battery Storage: The Complete 2026 Guide for Home...

    Aug 24, 2026
    Commercial rooftop solar panels at sunset with American flag — ITC safe harbor and commence-construction rules for 2026

    ITC Safe Harbor & Commence-Construction: What Solar Buyer...

    Aug 17, 2026
    Solar panel modules stacked at a U.S. port facility with customs documentation overlay, representing Section 232 tariff compliance for solar imports

    Section 232 Solar Tariffs & Minimum Import Prices: The De...

    Aug 14, 2026
    Close-up of an electrical breaker panel with a licensed electrician testing circuits with a multimeter

    How to Size Circuit Breakers: NEC 125% Rule (2026)

    Aug 12, 2026
    Container port at golden hour with crane lifting crated solar panels over the dock

    Solar Module Sourcing in 2026: Regional Costs, Tariff Sta...

    Aug 09, 2026
    Pallets of stacked solar modules in a bright distribution warehouse with forklift and conduit racks

    Module Prices Hit $0.34/W — So Why Did Your Commercial Qu...

    Aug 08, 2026
    Two installers finishing a residential rooftop solar installation at sunset

    The Safe Harbor Deadline Passed. Here's What Actually Hap...

    Aug 07, 2026
    Worker in cleanroom suit inspecting a silicon ingot at a solar polysilicon factory, shipping containers beyond the window

    Section 232 Polysilicon Tariffs Hit Solar: What August 20...

    Aug 06, 2026
    Technician's hands with clipboard and tablet inspecting a home standby generator, shallow depth of field

    Generac Generator Warranty Explained: 5, 7, and 10-Year E...

    Aug 03, 2026
    Residential standby generator installed beside a modern suburban home's electrical service panel at golden hour

    Whole Home Generator Sizing Guide 2026: How Many kW Do Yo...

    Aug 03, 2026
    Wall-mounted home battery storage unit installed in a garage beside a solar inverter

    Battery Storage Incentives by State: 2026 Rebate Programs...

    Jul 30, 2026
    Rows of solar panels in a distribution warehouse, tied to 2026 supply and pricing trends

    Solar Market Outlook H2 2026: Panel Prices, Supply Chain,...

    Jul 29, 2026
    Imported solar panels in shipping crates at a port, subject of 2026 tariff updates

    Solar Industry Tariff Updates: What Installers Need to Kn...

    Jul 27, 2026
    A city skyline at dusk with glowing windows and power transmission lines in the foreground

    Growing Electricity Demand: Why Energy Policy Reform Is M...

    Jul 24, 2026
    A technician installing a wall-mounted mini-split heat pump indoor unit in a bright modern living room

    Mini Split Installation Cost (2026): Equipment, Labor & E...

    Jul 23, 2026
    Solar panels elevated over green farmland with sheep grazing beneath

    Harnessing the Sun and Soil: How Agrivoltaics is Revoluti...

    Jul 21, 2026
    A showroom display of several brand-new black solar panel models angled on stands

    Newest Solar Panels in 2026: Latest Models from Leading U...

    Jul 18, 2026
    From the Field: A Master Electrician's Guide to Solar Commissioning

    From the Field: A Master Electrician's Guide to Solar Com...

    Jul 15, 2026
    A home energy storage system with a smart meter showing zero grid flow

    How Can a Residential ESS Achieve 0W Grid Flow?

    Jul 14, 2026
    Close-up of an automatic transfer switch panel with conduit in a residential utility room

    How Automatic Transfer Switches Work

    Jul 12, 2026
    A large residential rooftop fully covered with solar panels on a sunny day

    Solar Panels for 10,000 kWh/Month: 2026 Sizing Guide

    Jul 06, 2026
    7 Benefits of Switching to Commercial Solar Energy

    7 Benefits of Switching to Commercial Solar Energy

    Jun 30, 2026
    2026 H1 Solar Industry Recap: Record Installations, Tariff Uncertainty, and Storage Dominance

    2026 H1 Solar Industry Recap: Record Installations, Tarif...

    Jun 30, 2026
    How to Successfully Implement Solar Energy in Your Business

    How to Successfully Implement Solar Energy in Your Business

    Jun 30, 2026
    Three different solar panel types displayed side by side on stands outdoors

    The Main Types of Solar Panels: Which Should You Choose?

    Jun 26, 2026
    After Nearly 20 Years, America's Biggest Clean Energy Project Is Finally Operational

    America's Largest Clean Energy Project Goes Live After Ne...

    Jun 26, 2026
    Procurement Strategy: How to Navigate Solar Equipment Sourcing in 2026

    Procurement Strategy: How to Navigate Solar Equipment Sou...

    Jun 15, 2026
    A friendly solar consultant shaking hands with a homeowner on a sunny driveway

    How to Find Local Solar Companies Near Me

    Jun 14, 2026
    How Long Do Solar Panels Last? (2026 Guide)

    How Long Do Solar Panels Last? (2026 Guide)

    Jun 14, 2026
    A homeowner in conversation with a solar consultant on a sunny driveway

    What Questions Should I Ask My Solar Company?

    Jun 14, 2026
    A homeowner on the porch of a solar-equipped suburban home reviewing an energy bill

    Is Solar Worth It for My Home?

    Jun 10, 2026
    A homeowner and contractor reviewing permit paperwork on a clipboard in front of a house with new solar panels

    What Are Solar Permits and How Long Do They Take?

    Jun 07, 2026
    A homeowner at a kitchen table with a calculator and solar quotes

    Solar Panel Cost in 2026: What You'll Actually Pay

    Jun 06, 2026
    How Much Money Can I Save With Solar Panels?

    Solar Panel Savings in 2026: Real Numbers by State

    May 30, 2026
    The New York State Capitol area skyline with rooftop solar installations in the foreground

    New York Boosts Solar Investment in 2027 State Budget

    May 29, 2026
    A compact modular microinverter unit being mounted beneath rooftop solar panels by an installer

    Mango Power modular microinverter hits US residential sol...

    May 29, 2026
    A futuristic solar panel manufacturing facility with robotic arms and rows of new modules

    How Tesla Plans to Scale Solar Production to 100GW by 2028

    May 25, 2026
    A vast Australian solar farm with rows of panels and large battery storage containers

    NSW Seeks 2.5 GW Renewable Capacity, 12 GWh Storage Under...

    May 21, 2026
    Solar Workforce Crisis 2026: Installer Shortage, Training Programs, and Electrician Demand

    Solar Workforce Crisis 2026: Installer Shortage, Training...

    May 15, 2026
    Cows grazing in a green alpine pasture beneath elevated solar panels

    Nestlé Launches Agri-PV “Cow Solar” Project in Allgäu, Bl...

    May 04, 2026
    A row of suburban homes with rooftop solar and small battery cabinets

    FranklinWH Systems to Launch First U.S. City-Owned Reside...

    May 01, 2026
    Three sleek white home battery units wall-mounted in a row in a modern garage

    Tesla Expands Energy Solutions with Three-Phase Powerwall 3P

    Apr 26, 2026
    Solar panel canopies over a California school campus parking lot

    School District in California Deploys 3.1 MW Solar System...

    Apr 14, 2026
    The Future of Solar: 7 Breakthrough Technology Trends in 2026 — Portlandia Electric Supply

    The Future of Solar: 7 Breakthrough Technology Trends in ...

    Apr 12, 2026
    Trainees in safety vests learning solar panel installation at a training facility

    New York Boosts Renewable Workforce Funding with $50 Mill...

    Apr 05, 2026
    Pallets of wholesale solar panels stacked in a warehouse for EPC and installer buyers

    Wholesale Solar Panels: The Complete B2B Procurement Guid...

    Mar 13, 2026

    Get Price Drops & Product Releases

    Weekly digest for installers and project managers — price drops, new stock, NEC code updates.

    PES Supply, a PES Global Group Company