Generator Install Specification Guide for Electricians (7-2000 kW)
Standby generator specification, ATS selection, fuel-line sizing, exhaust routing, load calculations, NEC 700/701/702 code compliance, and the Generac, Kohler, Cummins, and Caterpillar SKUs stocked or drop-shipped through PES.
Generator sizing is the number-one source of specification error on commercial standby installations. Contractors who size on connected kW instead of running kW plus starting kVA either specify a generator too large (wasting $20,000-$100,000) or too small (which stalls at motor start and drops the entire load).
The three questions:
- What is the running load? Continuous load in kW after all motor-start transients have settled. From measured demand data or NEC 220 calculation.
- What is the largest single motor? Motor inrush current, expressed as kVA (locked-rotor code letter from NEMA MG 1 or the motor nameplate).
- What is the acceptable voltage sag? Standby generators allow 20-30% voltage sag during motor start. If sensitive loads (VFDs, computers) require < 15% sag, the generator must be oversized 30-50%.
Use the load calculator to combine running load and starting kVA. Manufacturer sizing software (Generac PowerDesign, Kohler Genset Sizer, Cummins GenSize) is more accurate than rules of thumb.
| Article | System Class | Typical Load | Transfer Time | Fuel Requirements |
|---|---|---|---|---|
| 700 | Emergency | Life safety, egress lighting, fire pumps | ≤ 10 sec | On-site fuel ≥ 2 hrs OR 24-hr from off-site source |
| 701 | Legally Required Standby | Communications, sewage, industrial process | ≤ 60 sec | On-site fuel ≥ 2 hrs |
| 702 | Optional Standby | Any load not classified as 700 or 701 | Not specified | Contractor / owner specifies |
| 708 | COPS (Critical Operations Power Systems) | Life-safety command centers, first responder | ≤ 10 sec | 72 hr on-site, redundant |
The automatic transfer switch (ATS) is often more scrutinized than the generator itself. Three-position ATS (Normal, Emergency, Off), open transition or closed transition (paralleled), rated at the generator output kVA. Selection factors:
- Transition type — Open-transition (100 ms outage during transfer) fine for most commercial. Closed-transition (paralleled with utility for 100 ms, then utility source disconnects) required for data centers and mission-critical.
- Withstand rating — UL 1008 (2016) requires ATS withstand rating ≥ available fault current at the ATS location. Typically 22-42 kAIC for commercial, 65-100 kAIC for industrial.
- Bypass isolation — Larger ATS (typically ≥ 600 A) offer bypass-isolation feature so the ATS can be serviced without interrupting load. Adds ~15-25% to ATS cost but pays back in maintenance downtime.
- Service entrance rated — ATS can serve as the service entrance disconnect (per NEC 230). Adds ~20% cost but eliminates a separate service disconnect.
-
1
Step 1 — Site survey and load study
Measure existing load (30 days recorded data preferred), identify largest motor, plan ATS location within 25 ft of service disconnect (NEC 230.72(A)).
-
2
Step 2 — Generator sizing calculation
Manufacturer software: input all motors with locked-rotor codes, all resistive loads, and voltage sag tolerance. Result is genset kW rating.
-
3
Step 3 — Fuel selection
Natural gas (cheapest, unlimited runtime, no on-site storage), LP (2 hr on-site tank standard, quick deploy), diesel (highest kW density, 72-hr runtime standard on 500 gal tank).
-
4
Step 4 — Pad and structural
Concrete pad sized per genset weight (typically 6" thick, 12" wider than skid). Level within 1" over the pad. Structural review for > 100 kW gensets.
-
5
Step 5 — Fuel line sizing
Natural gas: 5 psi max at meter, pipe sized per genset manufacturer flow at max load. LP: 11-14" WC at generator inlet. Diesel: 5/8" supply and 3/8" return lines standard.
-
6
Step 6 — Exhaust routing
Manufacturer-supplied silencer or aftermarket critical-grade for noise-sensitive locations. 10 ft minimum clearance from air intakes and 3 ft from combustible surfaces.
-
7
Step 7 — Genset electrical connections
AC output cables sized per NEC 445.13 (115% of nameplate). Neutral configuration: 3-pole ATS with neutral bond in generator (separately derived), or 4-pole ATS switching neutral (unbonded generator).
-
8
Step 8 — ATS installation and wiring
Mount within 25 ft of service disconnect. Wire utility-side, load-side, and generator-side feeders. Program timers: engine start delay, transfer delay, cool-down delay, retransfer delay.
-
9
Step 9 — Commissioning and load bank test
Full-load test with resistive load bank for 30 min per NFPA 110 Level 1 systems. Verify voltage regulation, frequency stability, load acceptance response.
-
10
Step 10 — Documentation and turnover
Deliver O&M manuals, factory test reports, load bank certification, ATS programming sheet, and warranty registration to owner. Schedule 30-day and 6-month follow-up.
Fuel selection drives long-term operational cost and generator specification. The three practical fuels for commercial standby:
- Natural gas — Cheapest per hour of runtime (~$0.10-$0.15 per kWh at $8/MMBtu). Unlimited runtime (as long as gas main pressure holds). Best for utility outages driven by grid events. Weakness: gas mains can lose pressure in extended outages (hurricane, ice storm), so backup fuel plan recommended for critical loads.
- LP (propane) — Middle cost (~$0.20-$0.35 per kWh). Standard 500-1000 gal tank gives 24-72 hrs runtime. Best for residential and small commercial where natural gas is not available.
- Diesel — Highest fuel cost ($0.30-$0.50 per kWh) but highest kW density. Standard 500 gal sub-base tank gives 72 hrs at full load; larger day tanks and bulk storage for longer runtime. Best for hospitals, data centers, and any load requiring > 24 hr on-site fuel storage.
NFPA 110 Level 1 systems require 96-hr fuel supply for Class X, 4-hr for Class 4, decreasing to none for Class 0. Verify class in owner's specification before quoting.
Diesel gensets > 50 hp fall under EPA Tier 4 emissions requirements (Tier 4 Final for new installations since 2015). Louisville-metro installations also need Kentucky Division for Air Quality permits for gensets over specific thresholds — typically 100 kW+ for stationary compression-ignition (CI) engines running > 100 hrs/year.
Emergency-only gensets (limited to 100 hrs/year non-emergency operation) get streamlined permitting. Prime-power gensets require full permitting. Coordinate with the owner's environmental consultant before ordering.
Diesel gensets typically come with a sub-base fuel tank sized for 24-72 hrs runtime at full load. Tank options and code:
- UL 142 double-wall sub-base — Steel double-wall with interstitial monitoring. Standard on 100-2000 kW gensets.
- UL 2085 protected aboveground — Insulated and fire-rated tank; required in some jurisdictions for above-ground > 60 gal. Not common on rear-yard commercial installations.
- Day tanks — Small day tank (55-500 gal) at the genset with bulk storage remote. Fuel-transfer pump moves fuel between. Standard for large gensets and long-runtime installations.
Kentucky UST (underground storage tank) regulations (401 KAR 42) apply if fuel storage is buried. Louisville Metro fire marshal permit required for tanks > 660 gal aboveground. Coordinate with owner's fire and environmental consultants early in bid.
Every diesel genset needs to dissipate ~40-60% of fuel input energy as coolant heat. Cooling options:
- Belt-driven radiator (standard) — Integrated with the genset skid. Requires 2-4 ft clearance in front of the radiator for airflow. Ambient max typically 40°C for full-power output.
- Remote radiator — Radiator relocated 20-100 ft away with piping between genset and radiator. Required when genset is indoors with limited air-flow, or when radiator noise/heat cannot be near sensitive equipment. Adds $5,000-$25,000 to installation.
- City-water cooling — Heat exchanger cooled by potable or process water. Rarely used; typically only in specialized installations where radiator is not feasible.
Verify site air-flow calculations: the manufacturer publishes minimum air-flow (CFM) and maximum ambient temperature. Louisville summer highs of 95°F+ at rooftop are common; specify a genset rated for 50°C ambient or accept derated output at peak summer.
Diesel exhaust must be routed clear of building air intakes and combustible surfaces. Requirements:
- Silencer — Industrial-grade (10-15 dBA reduction), residential-grade (18-25 dBA), or critical-grade (30-35 dBA). Cost scales roughly linearly with dBA reduction.
- Exhaust routing — 10 ft minimum from any air intake; 3 ft from combustible siding; vertical stack recommended (heat rise carries away from building).
- Rain cap and thimble — Rain cap on the terminal end; roof or wall thimble sized 2" larger than exhaust OD for clearance and heat dissipation.
- Insulation — Ceramic-fiber blanket over indoor exhaust runs; keeps room temperature down and reduces burn hazard.
- Condensate drip leg — Low point in the exhaust run with a drain valve, particularly on long horizontal runs.
NFPA 110 Level 1 systems (hospitals, life safety) require weekly no-load exercise (5 min), monthly load exercise (30 min at ≥ 30% rating), and annual load-bank test at 100% rating for 4 hrs (or at 30% rating with augmented load per 8.4.2).
Level 2 systems (non-critical standby) require monthly exercise only; annual load bank recommended but not mandatory.
Contractor deliverables at turnover:
- O&M manuals (engine, alternator, controller)
- Commissioning report with load-bank data
- Factory test certificate
- ATS programming sheet
- Fuel-system schematics
- Exhaust routing single-line
- Warranty registrations
- Recommended maintenance schedule
- Local service-provider list (Generac, Kohler, Cummins dealer contacts)
Portlandia sells and drop-ships gensets from Generac, Kohler, Cummins, and Caterpillar. Load-bank testing service coordinated through PES service partners.
Fuel choice is often decided by utility infrastructure and owner preference more than by engineering. Key considerations:
Natural gas is preferred for buildings with existing gas service and where extended outages are unlikely. Advantages: unlimited runtime (as long as gas main pressure holds), no on-site fuel storage, cleanest emissions. Disadvantages: susceptible to gas-main pressure loss during widespread outages; lower kW density (typically 10-15% derated from diesel equivalent).
Diesel is standard for hospitals, data centers, and critical facilities requiring 72+ hr on-site fuel. Advantages: highest kW density, self-contained fuel supply. Disadvantages: monthly fuel exercise required (diesel deteriorates in storage); EPA Tier 4 emissions equipment required (expensive on larger units); air-quality permitting required.
Propane / LP is standard for residential and small commercial without gas service. Advantages: self-contained (500-1000 gal tank is standard), long shelf life (no deterioration). Disadvantages: highest fuel cost per kWh; tank installation adds $3,000-$8,000 to project.
Dual-fuel gensets (natural gas primary, propane backup, or propane primary with tank-swap capability) are available from all major OEMs for locations where fuel-diversity matters.
Louisville Metro noise ordinance limits sound to 60 dBA at property line during nighttime hours (10 PM-7 AM). Generators typically produce 80-95 dBA at 1 m without silencing. Mitigation options:
- Critical-grade silencer — 30-35 dBA reduction. Manufacturer option or aftermarket (Universal Silencer, Nelson Global).
- Level-4 enclosure — Weatherproof enclosure with sound-dampening insulation. Rated to 65 dBA at 7 m typical. Standard on new commercial gensets.
- Level-1 sound-attenuated enclosure — Rated to 60 dBA at 23 ft. Premium option for noise-sensitive locations (hospitals, schools, hotels).
- Site orientation — Face genset radiator toward building; genset acoustic footprint is asymmetric.
- Berms and walls — Sound barriers between genset and property line. Effective 5-15 dBA reduction depending on height and mass.
Verify site sound levels post-installation. Use SLM (sound level meter) at property line during full-load exercise. Louisville Metro Board of Health can require post-installation mitigation if complaints exceed the ordinance.
Data centers, hospitals, and mission-critical facilities require redundancy (N+1 or 2N configuration). Multiple gensets paralleled through a paralleling switchgear cabinet. Key features:
- Paralleling switchgear — Automatic synchronization (voltage, frequency, phase) before parallel breaker closes. Load-share on kW and kvar. Auto-start / auto-stop based on load demand.
- Common bus — All paralleled gensets connect to a common paralleling bus, then feed a distribution switchboard or MCC.
- Automatic load shed — On loss of one genset, non-essential loads shed automatically to keep essential loads powered.
- Utility parallel — Base-load or peak-shave operation where gensets run parallel with utility. Requires utility interconnection agreement, protective relays (25, 27, 32, 47, 59, 81), and reverse-power protection.
Portlandia works with ASCO, Cummins, and Kohler paralleling switchgear designs for > 1 MW installations.
NFPA 110 (Standard for Emergency and Standby Power Systems) governs testing and maintenance of Level 1 and Level 2 systems. Testing requirements:
- Level 1 initial acceptance — 4-hour continuous full-load test. Verify voltage regulation < ±3%, frequency regulation < ±0.5%.
- Level 1 monthly exercise — 30 min at ≥ 30% of nameplate rating. Automatic transfer switch cycled.
- Level 1 annual load bank — 4-hour test at rated load. Sequential load levels: 25%, 50%, 75%, 100%, each held 30 min. Actual building load can be augmented with resistive load bank.
- Level 2 monthly exercise — 30 min minimum. Load requirement less stringent.
- Level 2 annual load bank — recommended but not mandatory.
Documentation retention: test records for the life of the equipment. Facility manager keeps hard copy in the emergency generator room; contractor keeps electronic copy for warranty support.
Modern gensets integrate with the building automation system (BAS) via Modbus TCP, BACnet/IP, or Ethernet/IP. Data points typically exchanged:
- Genset status (running / stopped / fault)
- Fuel level (diesel or LP)
- Engine oil pressure, coolant temperature
- Alternator voltage, frequency, phase currents
- ATS position (utility / genset)
- Run hours, start count
- Fault codes and alarms
Integration allows the facility manager to monitor genset health from the BAS front-end, receive alerts on faults, and correlate genset operation with utility outages. Cost: $500-$2,000 for the communication module and $2,000-$8,000 for BAS integration engineering.
Every commercial genset turnover should include hands-on training for the owner's facility staff:
- Monthly exercise procedure — how to initiate, what to observe, what to record.
- Fuel level check and refill procedure.
- ATS manual operation — how to transfer to genset manually, and back.
- Emergency shutdown — where the e-stop is, when to use it.
- Alarm response — what each fault code means, who to call.
- Service log — where to record hours, alarms, and service events.
Deliver: quick-reference laminated card, phone-numbers of OEM service and authorized dealer, PES service manager direct line, and a 30-day follow-up visit at no cost to verify the owner is comfortable operating the system.
Standby vs prime vs continuous — what is the difference?
Do I need a load bank test?
Can I parallel a portable rental generator with the permanent standby?
What is the minimum concrete pad size?
How is the neutral configured — bonded generator or unbonded?
What warranty do commercial generators carry?
Order Standby Generators and ATS from PES
Generac, Kohler, Cummins, Caterpillar gensets 7 kW to 2 MW. Louisville dealer network with commissioning support.
Register Now






































